Generating Stations near Northampton NN7, in North Northamptonshire council.
As of October 2026, Green Hill Solar Farm is at this stage: Decision made. A decision has been made. Our source doesn't say whether it was approved or refused, or whether work has started, so follow the link to check.
When: Decided October 2026
Green Hill Solar Farm consists of an electricity generating station with a capacity of up to 500 megawatts (MW) comprising of ground mounted solar arrays and associated development including energy storage, grid connection infrastructure and other infrastructure integral to the construction, operation and maintenance of the scheme.
See the area today on Google Street View
National infrastructure projects: Planning Inspectorate and planning.data.gov.uk, Open Government Licence v3.0. Headline schemes: kept by hand from the source named on each, checked October 2026.