Country England and Wales › Region South East › Council Windsor and Maidenhead › Neighbourhood Cox Green › Postcode SL6 3NY What's changing near SL6 3NY Within 2 km, around Cox Green in Windsor and Maidenhead. Building, planning, schools, transport, prices and crime.
103 new homes completed within 2 km, last 2 years
0 homes given permission on brownfield sites since 2021
+2.5% like-for-like prices in Cox Green, 2024 → 2025 (council +1.8%)
-7% recorded crime, last 12 months vs the 12 before
On the map
New homes School opened School closed Extended home Energy projectBlack pin: the postcode. Tap a dot for details.
Nearby, most recent first New homes 20 new homes completed houses · Jul 2026 – Oct 2026
planned Oct 2026 2.0 km away New homes 14 new homes completed flats · Oct 2026
planned Oct 2026 800 m away New homes 48 new homes completed flats · Jul 2026 – Sep 2026
Sept 2026 800 m away New homes 5 new homes completed houses · Aug 2026
Sept 2026 1.6 km away New school Jan 2023 1.3 km away School closed School closed: Redroofs School for the Performing Arts Other independent school, other independent school (de-registered)
Oct 2020 1.9 km away New-home postcodes with fewer than 5 homes are counted above but not listed. 11 postcodes nearby had new homes completed in the last two years.
18 homes extended 2021–2025, typically adding 28 m²
32 since energy certificates began (2008)
5 in SL6 3NY itself
Extended certificate 2025 Extended certificate 2014 Extended certificate 2014 Extended certificate 2014 Extended certificate 2014 Spotted when a home's energy certificate shows at least 15 m² (and 15%) more floor area than an earlier one. Only homes with two certificates show up, so the real number is higher. A busy street suggests extensions get permission here; check the council's planning register for the details.
Storm overflows within 2 km No monitored sewer storm overflows within 2 km (England only).
Environment Agency event duration monitoring, 2025 annual return (OGL; © Environment Agency copyright and/or database right 2026). Overflows release diluted sewage into rivers and the sea when sewers are overwhelmed, mostly after heavy rain.
Solar, wind and battery projects within 10 km 13 planned, approved or being built and 3 running (51 MW between them). Those within 5 km are on the map above.
Rooftop solar Furze Platt Senior School, Furze Platt Road - Solar Panels Approved, not yet built · 250 kW
May 2023 2.9 km away Rooftop solar Berkshire College Of Agriculture, Burchetts Green Road - Solar Panels Planning application in
May 2026 3.6 km away Solar farm Horizon, Hurley - Solar Panels Planning application in · 1 MW
Aug 2022 4.9 km away Rooftop solar Globe Business Park, Fieldhouse Lane - PV Panels Approved, not yet built
Jan 2023 6.6 km away Solar farm Billingbear Solar Farm Approved, not yet built · 22 MW
Jul 2024 6.8 km away Hydrogen Billingbear Solar Farm - Hydrogen Approved, not yet built
Jul 2024 6.8 km away Rooftop solar Lynch Hill School Primary Academy, Garrard Road - Solar Panels Approved, not yet built · 260 kW
Aug 2024 8.6 km away Rooftop solar Car Park Legoland Windsor Resort, Winkfield Road - PV solar photovoltaic Approved, not yet built · 1 MW
Jun 2024 8.6 km away Rooftop solar Thomas Road, Wooburn Industrial Estate - Solar Panels Approved, not yet built · 420 kW
Nov 2023 9.0 km away Energy from waste Slough Heat & Power Station Being built · 50 MW
May 2021 9.1 km away Road and street works within 1 km 7 permitted works running now or planned, 3 of them major.
Major Bannard Road, Maidenhead Utility asset works · CADENT GAS LIMITED · Some carriageway incursion
Aug 2026 to Oct 2026 150 m away Major, planned Webster Close, Maidenhead Highway repair and maintenance works · ROYAL BOROUGH OF WINDSOR AND MAIDENHEAD · Road closure
Jan 2027 to Jan 2027 350 m away Major Silvertrees Drive, Maidenhead Utility asset works · CADENT GAS LIMITED · Some carriageway incursion
Aug 2026 to Oct 2026 550 m away Standard Silvertrees Drive, Maidenhead Utility asset works · CADENT GAS LIMITED · Some carriageway incursion
Oct 2026 to Oct 2026 550 m away Standard Bracken Road, Maidenhead Utility repair and maintenance works · SOUTH EAST WATER · Some carriageway incursion
Jan 2027 to Jan 2027 950 m away Standard Lillibrooke Crescent, Maidenhead New service connection · SCOTTISH AND SOUTHERN POWER DISTRIBUTION (SSEPD) · Some carriageway incursion
Oct 2026 to Nov 2026 1000 m away Minor Bath Road, Maidenhead Highway repair and maintenance works · ROYAL BOROUGH OF WINDSOR AND MAIDENHEAD · Two-way signals
Oct 2026 to Oct 2026 850 m away DfT Street Manager permits (OGL), England. Dates are the planned ones; works often finish early or overrun.
Major infrastructure projects within 30 km Decided decided Sept 2016 2.7 km away Decided decided Nov 2023 9.0 km away Pre-application SDC M40 Campus Generating Stations · The site of the project is located in Buckinghamshire, England. It is approximately 2km to the west of Gerrards Cross, approximately 2.5km east of Beaconsfield and approximately 1.5km north of Hedgerley. The site comprises land immediately to the south of the A40 Oxford Road and immediately to the north of the M40 motorway. It has a history of landfill activities and is currently operated by Veolia for the landfilling of inert building waste (albeit the site no longer accepts any forms of waste). application due January 2027 14.0 km away Pre-application Heathrow West Airports · Heathrow Airport and land to the north-west and west of Heathrow Airport application due November 2027 19.7 km away Pre-application application due December 2027 21.4 km away Pre-application Transport schemes within 20 km Running nearest: Iomart, Clivemont Road - Solar Panels (rooftop solar, 2.9 km); Slough Sewage Treatment Works (other, 8.3 km); Fibrepower, Slough (energy from waste, 9.0 km).
DESNZ Renewable Energy Planning Database, April to June 2026 (OGL). Projects of 150 kW and over; refused, withdrawn and abandoned ones are left out.
Planning Inspectorate list of nationally significant infrastructure projects (roads, railways, energy, water, waste), October 2026 (OGL). Each is placed at one point, usually the middle of the site; long schemes run well beyond it.