Spotted when a home's energy certificate shows at least 15 m² (and 15%) more floor area than an earlier one. Only homes with two certificates show up, so the real number is higher. A busy street suggests extensions get permission here; check the council's planning register for the details.
Storm overflows within 2 km
2storm overflows within 2 km
7hours of spills in 2025 between them (typical neighbourhood: about 36)
8spill events counted
Severn Trent Water
Annesley Woodhouse- Forest Rd A Csointo Tributary Of River Erewash4 spills, 6 hours in 2025
200 m away
Severn Trent Water
Moseley Road Csointo Tributary Of The Dumbles4 spills, 2 hours in 2025
34 planned, approved or being built and 8 running (39 MW between them). Those within 5 km are on the map above.
Solar farm
Two Oaks Quarry, Coxmoor Road - Solar ArrayApproved, not yet built · 4 MW
Jan 2024 2.9 km away
Rooftop solar
Lamtek Limited, Wolsey Drive - Solar PanelsApproved, not yet built · 810 kW
Sept 2025 3.6 km away
Rooftop solar
Romo, Oddicroft Lane - Solar PanelsApproved, not yet built · 1 MW
May 2024 4.3 km away
Battery storage
Plymouth Avenue, Pinxton - Battery Energy Storage FacilityApproved, not yet built · 200 kW
May 2024 4.6 km away
Battery storage
Wharf Road & Beaufit Lane, Pinxton - Micro Energy StorageApproved, not yet built · 200 kW
Jan 2026 4.8 km away
Rooftop solar
Hucknall Leisure Centre, Linby Road - Solar PanelsApproved, not yet built
Feb 2025 5.1 km away
Rooftop solar
Lammas Leisure Centre, Lammas Road - Solar PanelsApproved, not yet built · 190 kW
Jan 2025 5.5 km away
Rooftop solar
Sherwood Way SouthApproved, not yet built · 3 MW
Sept 2021 5.6 km away
Battery storage
Mcdonalds, Mansfield Road - Micro Energy StoragePlanning application in · 200 kW
May 2026 5.9 km away
Rooftop solar
Brookside Way, Huthwaite - Solar PhotovoltaicsApproved, not yet built · 300 kW
May 2024 6.0 km away
Road and street works within 1 km
1 permitted works running now or planned.
Minor
Forest Road, Annesley WoodhouseNew service connection · CADENT GAS LIMITED · Two-way signals
Oct 2026 to Oct 2026 300 m away
DfT Street Manager permits (OGL), England. Dates are the planned ones; works often finish early or overrun.
Major infrastructure projects within 30 km
Pre-application
Chesterfield to WillingtonElectric Lines · Land between the Chesterfield Substation, south-east of Chesterfield and Willington Substation, east of Willington, Derbyshire.
Kestral Road - Battery Energy Storage FacilityApproved, not yet built
Dec 2023 6.1 km away
Rooftop solar
Eurocell Nickel, High View Road - Solar Pv SystemPlanning application in · 600 kW
Jul 2024 6.4 km away
Running nearest: Newstead and Annesley Wind Turbine (wind farm, 1.8 km); Crow Trees Farm (solar farm, 4.8 km); Sutton Landfill Site (landfill gas, 5.8 km); Twin Yards Solar Farm (solar farm, 6.8 km); Lindhurst Wind Farm (wind farm, 7.5 km).
DESNZ Renewable Energy Planning Database, April to June 2026 (OGL). Projects of 150 kW and over; refused, withdrawn and abandoned ones are left out.
Highways · From Farndon roundabout to Winthorpe roundabout near Newark-on-Trent
decided Oct 2025 29.2 km away
Planning Inspectorate list of nationally significant infrastructure projects (roads, railways, energy, water, waste), October 2026 (OGL). Each is placed at one point, usually the middle of the site; long schemes run well beyond it.