What's changing near L2 4TE
Within 2 km, around Pier Head in Liverpool. Building, planning, schools, transport, prices and crime.
1,432new homes completed within 2 km, last 2 years
0homes given permission on brownfield sites since 2021
+4.6%like-for-like prices in Pier Head, 2024 → 2025 (council +6.3%)
+7%recorded crime, last 12 months vs the 12 before
On the map
New homesSchool openedExtended homeStorm overflowEnergy projectBlack pin: the postcode. Tap a dot for details.
Nearby, most recent first
- New homes
6 new homes completedflats · Oct 2026
Oct 2026
1.4 km away - New homes
64 new homes completedflats · Sep 2026
Sept 2026
1.3 km away - New homes
45 new homes completedflats · Apr 2026
Apr 2026
2.0 km away - New homes
5 new homes completedflats · Jan 2026
Jan 2026
1.8 km away - New homes
6 new homes completedflats · Dec 2025
Dec 2025
950 m away - New homes
8 new homes completedflats · Nov 2025
Nov 2025
1.8 km away - New homes
81 new homes completedflats · Oct 2025
Nov 2025
1.8 km away - New homes
80 new homes completedflats · Oct 2025
Nov 2025
1.8 km away - New homes
64 new homes completedflats · Aug 2025 – Sep 2025
Sept 2025
750 m away - New homes
70 new homes completedflats · Aug 2025 – Sep 2025
Sept 2025
750 m away - New homes
72 new homes completedflats · Aug 2025 – Sep 2025
Sept 2025
750 m away - New homes
72 new homes completedflats · Aug 2025 – Sep 2025
Sept 2025
750 m away - New homes
87homes extended 2021–2025, typically adding 21 m²
166since energy certificates began (2008)
1in L2 4TE itself
Spotted when a home's energy certificate shows at least 15 m² (and 15%) more floor area than an earlier one. Only homes with two certificates show up, so the real number is higher. A busy street suggests extensions get permission here; check the council's planning register for the details.
Storm overflows within 2 km
10storm overflows within 2 km
2,471hours of spills in 2025 between them (typical neighbourhood: about 36)
385spill events counted
- United Utilities
Birkenhead Wwtw Birkeinto Mersey Estuary · near bathing water: Moreton; Wallasey105 spills, 1,273 hours in 2025
1.6 km away - United Utilities
Wallasey Ww Pumping Stationinto River Mersey Estuary · near bathing water: Wallasey; Moreton164 spills, 769 hours in 2025
1.7 km away - United Utilities
Birkenhead Wwtw Birkeinto River Birket (Great Culvert - Downstream Length) · near bathing water: Moreton; Wallasey41 spills, 226 hours in 2025
1.7 km away - United Utilities
Wallasey Ww Pumping Stationinto River Mersey Estuary · near bathing water: Wallasey; Moreton48 spills, 139 hours in 2025
1.7 km away - United Utilities
Woodside Csointo River Mersey Estuary (Tidal) · near bathing water: Wallasey14 spills, 60 hours in 2025
1.7 km away - United Utilities
St Nicholas Storm Sewer Overflowinto Mersey Estuary · near bathing water: Wallasey7 spills, 3 hours in 2025
550 m away - United Utilities
Gower St/Kings Dock Csointo Mersey Estuary4 spills, 1 hours in 2025
800 m away - United Utilities
Battery Lane Csointo The Mersey Estuary · near bathing water: Wallasey2 spills, 0 hours in 2025
1.9 km away
Environment Agency event duration monitoring, 2025 annual return (OGL; © Environment Agency copyright and/or database right 2026). Overflows release diluted sewage into rivers and the sea when sewers are overwhelmed, mostly after heavy rain.
Solar, wind and battery projects within 10 km
57 planned, approved or being built and 9 running (144 MW between them). Those within 5 km are on the map above.
- Rooftop solar
Port Of Liverpool Building, Mann Island - Solar PanelsApproved, not yet built
Feb 2026
400 m away - Rooftop solar
Mercedes-Benz, Pall Mall - Solar ArrayApproved, not yet built · 350 kW
Aug 2022
850 m away - Rooftop solar
Tipographic, Morpeth Wharf - Solar PV PanelsApproved, not yet built · 810 kW
May 2023
1.9 km away - Rooftop solar
Sainsburys, Jennifer Avenue - Solar panelsApproved, not yet built · 450 kW
Aug 2023
2.0 km away - Rooftop solar
HMS Eaglet, Sefton Street - Wind Turbine & Solar PanelsPlanning application in
Sept 2022
2.2 km away - Wind farm
HMS Eaglet, Sefton Street - Wind Turbine & Solar PanelsPlanning application in
Sept 2022
2.2 km away - Rooftop solar
North Liverpool Academy, Heyworth Street - Solar PV ArrayPlanning application in · 210 kW
Jul 2025
2.4 km away - Rooftop solar
Tesco SuperstoreApproved, not yet built
Apr 2021
2.9 km away - Rooftop solar
Huskisson Dock Building, Huskisson Dock - Solar PV ArrayApproved, not yet built · 1 MW
Mar 2024
3.0 km away - Rooftop solar
Steel Terminal, Royal Seaforth Dock - Solar PanelsApproved, not yet built
Mar 2024
3.2 km away
Road and street works within 1 km
14 permitted works running now or planned, 7 of them major.
- Major, planned
Lower Castle Street, LiverpoolStatutory Infrastructure Works · MANWEB · Road closure
Nov 2026 to Nov 2026
100 m away - Major
Lower Castle Street, LiverpoolStatutory Infrastructure Works · MANWEB · Road closure
Nov 2026 to Nov 2026
100 m away - Major, planned
Davies Street, LiverpoolHighway improvement works · LIVERPOOL CITY COUNCIL · Some carriageway incursion
Sept 2026 to Oct 2026
250 m away - Major, planned
Crosshall Street, LiverpoolUtility repair and maintenance works · MANWEB · Lane closure
Oct 2026 to Nov 2026
400 m away - Major, planned
New Quay, LiverpoolSection 50 · LIVERPOOL CITY COUNCIL · No carriageway incursion
Sept 2026 to Oct 2026
600 m away - Major
New Quay, LiverpoolSection 50 · LIVERPOOL CITY COUNCIL · No carriageway incursion
Sept 2026 to Oct 2026
600 m away - Major, planned
Concert Street, LiverpoolHighway improvement works · LIVERPOOL CITY COUNCIL · Some carriageway incursion
Sept 2026 to Nov 2026
750 m away - Standard
Hunter Street, LiverpoolUtility repair and maintenance works · MANWEB · Lane closure
Oct 2026 to Oct 2026
900 m away - Standard
Tabley Street, LiverpoolUtility asset works · ESP ELECTRICITY · Give and take
Nov 2026 to Dec 2026
950 m away - Minor
Major infrastructure projects within 30 km
- Pre-application
Mersey Tidal Power ProjectGenerating Stations · This will be an in-river proposal, located within the Mersey Riverine
environment. The Project will be located towards the mouth of the River
Mersey, between the Wirral on the west and Liverpool to the east. application due January 2028
1.1 km away - Decideddecided Sept 2014
15.8 km away - Pre-applicationapplication due April 2027
18.3 km away - Decideddecided May 2015
19.2 km away - Decisionapplication due Q3 2025
20.2 km away - Decision
Frodsham SolarGenerating Stations · Land on Frodsham Marsh, approximately 500m to the north of Frodsham, Cheshire West and Chester application due 30 May 2025
20.5 km away
Transport schemes within 20 km
None on our list yet. We're starting with recently opened and under-construction rail schemes.
Running nearest: Burbo Bank Energy Storage (battery storage, 4.4 km); Land at Carnegie Road (battery storage, 4.4 km); Lister Drive (battery storage, 4.4 km); Liverpool Energy Management Facility (battery storage, 4.4 km); Port of Liverpool - wind (wind farm, 4.9 km).
DESNZ Renewable Energy Planning Database, April to June 2026 (OGL). Projects of 150 kW and over; refused, withdrawn and abandoned ones are left out.
Planning Inspectorate list of nationally significant infrastructure projects (roads, railways, energy, water, waste), October 2026 (OGL). Each is placed at one point, usually the middle of the site; long schemes run well beyond it.