Spotted when a home's energy certificate shows at least 15 m² (and 15%) more floor area than an earlier one. Only homes with two certificates show up, so the real number is higher. A busy street suggests extensions get permission here; check the council's planning register for the details.
Storm overflows within 2 km
No monitored sewer storm overflows within 2 km (England only).
72 planned, approved or being built and 10 running (145 MW between them). Those within 5 km are on the map above.
Rooftop solar
Stanley Meat Market, Prescot Road - Solar PV SystemsApproved, not yet built · 300 kW
Jul 2024 950 m away
Battery storage
Lister Battery Limited - Battery Energy Storage SystemApproved, not yet built · 6 MW
Apr 2025 1.1 km away
Rooftop solar
The Big Yellow Self Storage, Mill Lane - Solar ArrayApproved, not yet built · 170 kW
May 2023 1.8 km away
Rooftop solar
North Liverpool Academy, Heyworth Street - Solar PV ArrayPlanning application in · 210 kW
Jul 2025 2.3 km away
Rooftop solar
Alder Hey Hospital, East Prescot Road - Solar PV ArrayApproved, not yet built · 470 kW
Mar 2026 2.3 km away
Rooftop solar
Sainsburys Supermarket, East Prescot Road - Solar PanelsApproved, not yet built · 460 kW
Jun 2025 2.5 km away
Rooftop solar
Sainsburys, Jennifer Avenue - Solar panelsApproved, not yet built · 450 kW
Aug 2023 3.0 km away
Rooftop solar
Dixons Croxteth Academy, Carr Lane East - Solar PanelsApproved, not yet built · 170 kW
Oct 2025 3.3 km away
Battery storage
Jeffrey Humble Playing Fields, Long Lane - Micro Energy Storage SystemApproved, not yet built · 200 kW
Sept 2025 3.6 km away
Rooftop solar
Mercedes-Benz, Pall Mall - Solar ArrayApproved, not yet built · 350 kW
Road and street works within 1 km
36 permitted works running now or planned, 28 of them major.
Major, planned
Oak Leigh, LiverpoolUtility asset works · Grain Communications Limited (formerly Solway Communications Limited) · Give and take
Nov 2026 to Dec 2026 100 m away
Major, planned
Ivy Leigh, LiverpoolUtility asset works · Grain Communications Limited (formerly Solway Communications Limited) · Give and take
Dec 2026 to Jan 2027 100 m away
Major
Ivy Leigh, LiverpoolUtility asset works · Grain Communications Limited (formerly Solway Communications Limited) · Give and take
Sept 2026 to Oct 2026 100 m away
Major, planned
Hilberry Avenue, LiverpoolUtility asset works · Grain Communications Limited (formerly Solway Communications Limited) · Give and take
Nov 2026 to Dec 2026 150 m away
Major, planned
Silverdale Avenue, LiverpoolUtility asset works · Grain Communications Limited (formerly Solway Communications Limited) · Give and take
Dec 2026 to Jan 2027 200 m away
Major
Silverdale Avenue, LiverpoolUtility asset works · Grain Communications Limited (formerly Solway Communications Limited) · Give and take
Sept 2026 to Oct 2026 200 m away
Major, planned
West Derby Road, LiverpoolNew service connection · CADENT GAS LIMITED · Lane closure
Dec 2026 to Dec 2026 250 m away
Major
West Derby Road, LiverpoolNew service connection · CADENT GAS LIMITED · Lane closure
Oct 2026 to Oct 2026 250 m away
Major, planned
Major infrastructure projects within 30 km
Pre-application
Mersey Tidal Power ProjectGenerating Stations · This will be an in-river proposal, located within the Mersey Riverine
environment. The Project will be located towards the mouth of the River
Mersey, between the Wirral on the west and Liverpool to the east.
Frodsham SolarGenerating Stations · Land on Frodsham Marsh, approximately 500m to the north of Frodsham, Cheshire West and Chester
application due 30 May 2025 18.8 km away
Pre-application
Intermodal Logistics Park NorthRail Freight Interchanges · Site known as Intermodal Logistics Park North – land bounded by the M6 motorway (west), Winwick Lane (south and east) and Chat Moss railway line (north).
Transport schemes within 20 km
None on our list yet. We're starting with recently opened and under-construction rail schemes.
The longer view
Like-for-like prices in Tuebrook: +41% over five years (2020 → 2025).
Council tax list: 20 homes added in the neighbourhood since April 2024.
Population (GP registrations): -0.6% in two years.
HyNet Carbon Dioxide PipelineOther Pipe-lines · From the Ince AGI in Cheshire, via Stanlow Refinery, to Talacre Beach in North Wales
decided Mar 2024 24.5 km away
Pre-application
Hynet North West Hydrogen PipelineGas Transporter Pipe-lines · An approximate 125km pipeline centred approximately 1km south west of Lower Whitley, Cheshire
application due Dec 2027 26.1 km away
Planning Inspectorate list of nationally significant infrastructure projects (roads, railways, energy, water, waste), October 2026 (OGL). Each is placed at one point, usually the middle of the site; long schemes run well beyond it.