Spotted when a home's energy certificate shows at least 15 m² (and 15%) more floor area than an earlier one. Only homes with two certificates show up, so the real number is higher. A busy street suggests extensions get permission here; check the council's planning register for the details.
Storm overflows within 2 km
7storm overflows within 2 km
194hours of spills in 2025 between them (typical neighbourhood: about 36)
32 planned, approved or being built and 15 running (73 MW between them). Those within 5 km are on the map above.
Solar farm
Lullington Solar ParkPlanning application in · 44 MW
Jul 2025 1.3 km away
Energy from waste
Keith Willshee Way - Swadlincote Resource Recovery ParkApproved, not yet built · 20 MW
Aug 2025 3.0 km away
Battery storage
Park Road, Overseal - Battery Storage FacilityApproved, not yet built · 50 MW
Jul 2025 3.6 km away
Battery storage
Mount Road, Castle Gresley - Battery Storage FacilityApproved, not yet built · 20 MW
Jul 2022 4.2 km away
Battery storage
Breach Farm - Energy BarnApproved, not yet built · 40 MW
Aug 2017 4.8 km away
Battery storage
Caldwell Road - Battery StorageApproved, not yet built · 90 MW
Jul 2024 5.8 km away
Rooftop solar
Meadowside Leisure Centre, High Street - Solar PanelsPlanning application in · 290 kW
Nov 2024 6.2 km away
Solar farm
Claymills Sewage Treatment Works, Meadow Lane - Solar PanelsPlanning application in · 25 MW
May 2026 7.0 km away
Battery storage
Burton Enterprise Park, Hawkins Lane - Battery Energy StorageApproved, not yet built
Jul 2022 7.0 km away
Rooftop solar
Velis Kebab, Hawkins Lane - Photovoltaic PanelsApproved, not yet built · 170 kW
Apr 2024 7.0 km away
Road and street works within 1 km
No road or street works with a permit running now or planned within 1 km (England; permits granted up to the end of September 2026).
DfT Street Manager permits (OGL), England. Dates are the planned ones; works often finish early or overrun.
Major infrastructure projects within 30 km
Pre-application
Castle Way EnergyGenerating Stations · The proposed development includes five development sites (Sites A-E) which are situated in the rural expanse between Derby, Uttoxeter and Ashbourne.
Clinitron House, Excelsior Road - Solar PanelsApproved, not yet built · 160 kW
May 2026 7.0 km away
Rooftop solar
Ceva House, Excelsior Road - Solar PanelsPlanning application in · 220 kW
Feb 2025 7.1 km away
Running nearest: Midland Lead, Kiln Way - Solar Photovoltaic Panels (rooftop solar, 1.4 km); Short Hazel Solar Farm (solar farm, 2.2 km); Bretby Power (landfill gas, 3.0 km); Prestop Park Farm (solar farm, 3.9 km); Land at Ingles Hill Farm (solar farm, 4.4 km).
DESNZ Renewable Energy Planning Database, April to June 2026 (OGL). Projects of 150 kW and over; refused, withdrawn and abandoned ones are left out.
Rail Freight Interchanges · 20km southwest of Nottingham, next to East Midlands Airport
Sept 2026 17.6 km away
Pre-application
Chesterfield to WillingtonElectric Lines · Land between the Chesterfield Substation, south-east of Chesterfield and Willington Substation, east of Willington, Derbyshire.
Planning Inspectorate list of nationally significant infrastructure projects (roads, railways, energy, water, waste), October 2026 (OGL). Each is placed at one point, usually the middle of the site; long schemes run well beyond it.