Spotted when a home's energy certificate shows at least 15 m² (and 15%) more floor area than an earlier one. Only homes with two certificates show up, so the real number is higher. A busy street suggests extensions get permission here; check the council's planning register for the details.
Storm overflows within 2 km
1storm overflows within 2 km
0hours of spills in 2025 between them (typical neighbourhood: about 36)
Daventry International Rail Freight Terminal Phase 4 (DIRFT 4)Storage or Distribution of Goods · The site extends to approximately 255 hectares and lies wholly within the administrative area of West Northamptonshire, c. 7km east of Rugby and c.11.5km north of Daventry. The M1 runs immediately adjacent to the western boundary of the Site, and it is located c.1km to the north of Junction 18 of the M1. DIRFT III (the latest phase of development at DIRFT) is located immediately west of the site across the M1 motorway. The site is c.1.3km to the north of the village of Crick and c.800m to west of the village of Yelvertoft.
Tanners Lane - Battery Energy Storage SystemApproved, not yet built · 30 MW
Jun 2025 4.7 km away
Rooftop solar
Mercedes Benz Coventry, John Wigley Way - Solar PV PanelsApproved, not yet built · 250 kW
Oct 2022 4.7 km away
Running nearest: Coventry (energy from waste, 6.4 km); Coventry National Grid Substation (battery storage, 6.9 km); Land South of Pogmore Spinney (solar farm, 7.5 km); Packington Generation Plant Phase 3 (landfill gas, 9.6 km).
DESNZ Renewable Energy Planning Database, April to June 2026 (OGL). Projects of 150 kW and over; refused, withdrawn and abandoned ones are left out.
Railways · Between Redditch and Alvechurch
decided Oct 2013 29.3 km away
Planning Inspectorate list of nationally significant infrastructure projects (roads, railways, energy, water, waste), October 2026 (OGL). Each is placed at one point, usually the middle of the site; long schemes run well beyond it.